Road Department

Select Projects

Bus Rapid Transit Route (BRT)

PUNE BRT BACKGROUND

  • Pune got approval of BRT project with Network Length- 68.80 km under JnNURM with Sanctioned Cost- Rs 1013.97 crores
  • 16 Km of the stretch out of planned network of 68.80 kms is completed
  • BRT has route along Vishrantwadi to 2015, also Nagar road BRT will be functioning by April 2016
  • Based on the learning experience from the Pilot BRT, public perception and the system as paradigm, PMC would like to extend the same for the balance

Road department has carried out development of 2 BRT routes

  1. Vishrantwadi - Alandi
  2. Yeravada-Wagholi Route

Network Expansion

After experiencing the 16km Rainbow network in Pune today, people are demanding more. Quick expansion is on the cards with 15 km Rainbow corridors under planning and designing. The city is also redesigning 15km of Pilot BRT corridors on the lines of Rainbow infrastructure. Additional corridors are coming up in Pimpri-Chinchwad too. When these corridors in the planning phase would be completed, the Rainbow network in the Pune Metropolitan Region will be more than 90 km, providing rapid, "Rainbow'' mobility to more than 7 lakh commuters by next year.